Sheremetyevo Airport reports sharp rise in profit and revenue for 2019

Revenue increased by 41.6% compared to the same period last year and amounted to 82,088 million rubles.

Operating profit increased by 38.8% compared to the same period last year and amounted to 27,083 million rubles.

Reconstruction of Runway-1 is on schedule, with completion expected by the end of 2020.

Sheremetyevo International Airport Joint Stock Company (SVO JSC) reported revenue of 82,088 million rubles for 2019, and increase of 41.6% over last year, and an operating profit of 27,083 million rubles, an increase of 38.8% over 2018.

IFRS Key Figures

Indicator Description
12 months
 
2018
2019
changes
Passenger traffic (thousands of people)
45 836
49 932
8.9%
Revenue (mln rubles)
57 980
82 088
41.6%
Operating expenses (mln rubles)
38 467
55 005
43%
Operating profit (mln rubles)
19 513
27 083
38.8%
Net profit for the period from continuing operations (mln rubles)
11 021
22 341
102,7%

The audited consolidated financial statements of SVO JSC and its subsidiaries (the Group) for 2019 were approved at a regular meeting of the board of directors. The financial statements were prepared in accordance with the requirements of International Financial Reporting Standards (IFRS) and reviewed by the independent auditor Ernst & Young LLC.

Reconstruction of runway and apron are proceeding on schedule.

The Board of Directors also approved the progress report on the project to reconstruct Runway 1 and the western section of the apron, which will be rebuilt to accommodate parking for aircraft and house a number of other airport facilities. To ensure the reconstruction of these facilities at the airport, a crushing-and-screening complex and two concrete plants have been installed. More than 900 workers and specialists, 35 units of special equipment and 215 dump trucks were involved.

At this stage, the removal of the pavement on old Runway-1 has been completed, and work is underway on the arrangement of soil, the installation of engineering networks and new Runway-1 coatings. Work is being done regularly and is ahead of schedule. The work is scheduled to be completed by the end of this year.