The assembly of Il-76МD-90А is being carried out by Aviastar-SP. The first test aircraft will soon be energized, press-service of Aviastar-SP reports. AEX.ru
All the enterprise’s labor resources and the most advanced technologies are involved in the process. At present the work on airframe has been completed and the installation of systems and equipment is in progress. The cockpit is currently being complemented. The work on pressurization and pressure testing of airframe’s compartments is also underway.
«Now all the electric wiring harness and electric boxes have been mounted, the wire identification and power supply using rig’s special current will be completed. And then the final adjustment of the systems using ground power supply and hydraulic test rigs will be started», - Valery Tokarev, the Deputy Director General of Aviastar-SP noted.
After the completion of final assembly the testing of the aircraft will be started.